KEEL LAYING CEREMONY HELD FOR FIRST CANADIAN JOINT SUPPORT SHIP
Thursday, January 16, 2020

Source: Canadian Forces


OTTAWA -- A keel laying ceremony was held January 16 for the first of two Canadian Joint Support Ships being built at Seaspan's Vancouver Shipyards. The ships are being built using modular construction methods, and so they lack a keel that runs the length of the ship. The milestone was celebrated with the laying of a ceremonial coin near the center section of the lead ship, the future HMCS Protecteur.

Initial construction of the first ship began with a steel-cutting ceremony in June 2018, but a full construction contract to finish the ship is expected in spring 2020.

The new class is using an off-the-shelf ship design from ThyssenKrupp Marine Systems Canada. The long-delayed effort will replace Canada's former supply ships, HMCS Preserver and HMCS Protecteur (the new class will reuse the names of the old auxiliaries). The replacement effort was originally launched in 2004, but the initial attempt was canceled in 2008 because of high costs. The original Preserver and Protecteur were removed from service ahead of schedule in 2014, leaving a capability gap that has been filled through agreements to utilize foreign logistics ships and the conversion of a container ship into an interim supply ship.

JSS delivery dates have been pushed back multiple times. At one point, the first ship was expected to arrive by 2020, but delivery will not take place until 2023. The second ship is not expected to arrive until 2025.

In October 2019, Navamar was awarded a CAD11.7 million contract for five ship-to-shore connector craft that will eventually be used by the JSS fleet.

 

NOTICE TO USERS

Warranty: Forecast International makes no guarantees as to the veracity or accuracy of the information provided. It warrants only that the information, which has been obtained from multiple sources, has been researched and screened to the best of the ability of our staff within the limited time constraints. Forecast International encourages all clients to use multiple sources of information and to conduct their own research on source data prior to making important decisions. All URLs listed were active as of the time the information was recorded. Some hyperlinks may have become inactive since the time of publication.

Technical Support: Phone (203)426-0800 e-mail support@forecastinternational.com

Subscription Information: Phone (203)426-0800 or (800)451-4975; FAX (203)426-0223 (USA) or e-mail sales@forecastinternational.com

Aerospace/Defense News Highlights is published by Forecast International, 75 Glen Rd, Suite 302 Sandy Hook, CT 06482 USA. Articles that list Forecast International as the source are Copyrighted © 2024. Reproduction in any form, or transmission by electronic or other means, is prohibited without prior approval from the publisher.

Forecast International welcomes comments and suggestions regarding its material.
Please send any feedback to: info@forecastinternational.com