Dorad Commissioning Continues; 800 MW Due by December

Dorad Commissioning Continues; 800 MW Due by December

Source: Dorad Energy


ELLOMAY CAPITAL ANNOUNCES THE CONNECTION OF THE DORAD POWER PLANT TO THE ISRAELI NATIONAL GRID
Thursday, August 1, 2013
Dorad Commissioning Continues; 800 MW Due by December

Dorad Commissioning Continues; 800 MW Due by December

Source: Dorad Energy


TEL AVIV, Israel - Ellomay Capital has received a notice from Dorad Energy - in which it indirectly holds 7.5 percent (with an option to increase such holdings to 9.375 percent) - that the 400-kV GIS substation serving the power plant constructed by Dorad has been energized and connected to the Israeli national grid. Based on the notice received from Dorad, the first six gas turbines (each with a 48-MW capacity) are expected to be commissioned in simple cycle during the next few weeks, with all 12 gas turbines planned to be fired by the end of August. Commissioning of the heat recovery boilers and the steam turbines will take place from September through November, with acceptance tests for the entire combined-cycle Dorad power plant currently scheduled to take place in December. Pursuant to the notice received from Dorad, the Dorad power plant is currently expected to start commercial operation and production of power at its full capacity of approximately 800 MW in January 2014.

Ellomay's main assets include 12 photovoltaic plants in Italy with an aggregate capacity of approximately 22.8 MW (six in the Puglia region, four in the Marche region, and two in the Veneto region), 85 percent ownership of a photovoltaic plant in Spain with a capacity of approximately 2.3 MW, and 7.5 percent indirect holdings in Dorad (with an option to increase such holdings to 9.375 percent), Israel's largest private power plant, which is in the final stages of construction and is expected to have an aggregate capacity of approximately 800 MW (representing approximately 8 percent of Israel's current electricity consumption).

Source: http://www.ellomay.com/files/SEC_Filing/new/2013/Form6-K-July-3-2013.pdf
Associated URL: http://www.ellomay.com
 

NOTICE TO USERS

Warranty: Forecast International makes no guarantees as to the veracity or accuracy of the information provided. It warrants only that the information, which has been obtained from multiple sources, has been researched and screened to the best of the ability of our staff within the limited time constraints. Forecast International encourages all clients to use multiple sources of information and to conduct their own research on source data prior to making important decisions. All URLs listed were active as of the time the information was recorded. Some hyperlinks may have become inactive since the time of publication.

Technical Support: Phone (203)426-0800 e-mail support@forecastinternational.com

Subscription Information: Phone (203)426-0800 or (800)451-4975; FAX (203)426-0223 (USA) or e-mail sales@forecastinternational.com

Aerospace/Defense News Highlights is published by Forecast International, 75 Glen Rd, Suite 302 Sandy Hook, CT 06482 USA. Articles that list Forecast International as the source are Copyrighted © 2024. Reproduction in any form, or transmission by electronic or other means, is prohibited without prior approval from the publisher.

Forecast International welcomes comments and suggestions regarding its material.
Please send any feedback to: info@forecastinternational.com