FORTUM COMPLETES CONSTRUCTION OF UNIT 3 AT NYAGAN POWER PLANT IN RUSSIA
Monday, September 29, 2014
Nyaganskaya features the Siemens SGT5-4000F gas turbine

Nyaganskaya features the Siemens SGT5-4000F gas turbine

Source: Siemens


ST. PETERSBURG - The third unit at Fortum's Nyagan Power Plant has passed comprehensive and certification tests that precede commissioning. Fortum plans to start the commercial operation of the unit by the end of 2014. Capacity payments under the Russian government's Capacity Supply Agreement (CSA) for 418 megawatts (MW) are scheduled to start as of 1 January 2015.

During the testing period, the unit operated for 72 hours at maximum load. After the comprehensive tests, the power plant began certification tests to confirm the unit's technical parameters. Certification was passed successfully. The unit was thereby finalized 15 months ahead of the CSA-projected schedule. Nyagan 1 has been in commercial operation since 1 April 2013 and Nyagan 2 since 1 December 2013. Construction of the power plant began in 2008.

The Nyagan Power Plant that has now been completed in the oil and gas rich Russian Khanty-Mansiysk Automonous Region in Western Siberia was Fortum's largest green-field investment project in the 2000's. With a power generation capacity of over 1,260 MW, it is also Russia's most modern thermal power plant and the country's biggest combined-cycle gas turbine (CCGT) facility in decades. The power plant features the most advanced available thermal generation technologies and is unrivaled in efficiency for its class in Russia.

With the Nyagan project successfully completed, Fortum once again demonstrates its commitment to fulfill its extensive 2,500-MW investment program that will have nearly doubled the company's power generation capacity in Russia once finalised in 2015. Fortum now focuses on the completion of the program's last two remaining new units that are being built at the Chelyabinsk GRES power plant. The two units will add close to 500 MW's of new power generation capacity and 350 MW's of heat production capacity to support the demand from the local metals and heavy machinery industries in the Urals region.

Source: http://www.fortum.com/en/mediaroom/pages/fortum-completes-construction-of-unit-3-at-nyagan-power-plant-in-russia.aspx
Associated URL: http://www.fortum.com/en/mediaroom
 

NOTICE TO USERS

Warranty: Forecast International makes no guarantees as to the veracity or accuracy of the information provided. It warrants only that the information, which has been obtained from multiple sources, has been researched and screened to the best of the ability of our staff within the limited time constraints. Forecast International encourages all clients to use multiple sources of information and to conduct their own research on source data prior to making important decisions. All URLs listed were active as of the time the information was recorded. Some hyperlinks may have become inactive since the time of publication.

Technical Support: Phone (203)426-0800 e-mail support@forecastinternational.com

Subscription Information: Phone (203)426-0800 or (800)451-4975; FAX (203)426-0223 (USA) or e-mail sales@forecastinternational.com

Aerospace/Defense News Highlights is published by Forecast International, 75 Glen Rd, Suite 302 Sandy Hook, CT 06482 USA. Articles that list Forecast International as the source are Copyrighted © 2024. Reproduction in any form, or transmission by electronic or other means, is prohibited without prior approval from the publisher.

Forecast International welcomes comments and suggestions regarding its material.
Please send any feedback to: info@forecastinternational.com